CISA Information Systems Acquisition, Development and Implementation: 348 practice questions
12 of the 348 Information Systems Acquisition, Development and Implementation questions in the Certsqill CISA bank, shown in full below. Each one carries an explanation for every option, not just the correct one — the wrong answers are where the marks go.
Preparing for CISA? Take the free 5-min readiness check →
1. Approved steering minutes record scope: Which evidence is BEST?
- Approved steering minutes record scope, cost, risk, and sponsor authorization. ✓Approved minutes directly evidence governance review and authorization.
- A developer’s meeting notes describe the preferred design and expected implementation schedule.Developer notes lack evidence of sponsor or steering authorization.
- A project manager’s spreadsheet lists estimated costs and current milestones.The spreadsheet shows information but not authorized governance decisions.
- An email from the vendor confirms that configuration work has started.Vendor activity does not demonstrate internal authorization of major changes.
Approved steering minutes directly document authorization of major project decisions.
2. Require a complete business case before approval: Which gap is MOST consequential?
- Request updated cost estimates and implementation dates before reconsidering approval.Additional estimates leave alternatives, benefits, feasibility, and implementation risks unresolved.
- Require a complete business case before approval. ✓Approval lacks alternatives, operational feasibility, risks, and measurable benefits needed for informed authorization.
- Approve because technical feasibility and the cheapest vendor were demonstrated.Technical feasibility and price alone cannot establish value, practicality, or acceptable implementation risk.
- Require more vendor references and technical demonstrations before proceeding with approval.References and demonstrations do not replace missing business-case decision criteria.
Approval requires alternatives, feasibility, risks, and measurable benefits, not merely technical success.
3. Trace high-risk requirements through testing: What should the auditor do NEXT?
- Repeat unit-test sampling.Repeating technical testing does not address missing business acceptance evidence.
- Compare sprint velocity with the project baseline and investigate variances.Velocity does not demonstrate requirements coverage or authorized business acceptance.
- Trace high-risk requirements through testing and acceptance. ✓Traceability through authorized acceptance addresses the identified agile control gap.
- Review the deployment calendar, budget status, and planned release milestones.Scheduling and budget evidence does not resolve high-risk acceptance uncertainty.
The next procedure should test traceability from high-risk requirements through authorized acceptance.
4. Separate payment preparation from approval before: What response is MOST appropriate?
- Accept the proposal because postdeployment review detects unusual payments.Detection after deployment does not prevent incompatible payment authority.
- Separate payment preparation from approval before development. ✓Segregation should be defined and embedded before implementation begins.
- Ask developers to decide whether segregation is technically convenient.Control requirements belong to accountable management, not developer preference.
- Recommend documenting the control after deployment once actual workflows become clearer.Deferring requirements increases redesign and control failure risk.
Management should define segregated preparation and approval before system development.
5. Report that readiness and authorized acceptance remain: What is the auditor’s BEST conclusion?
- Report that readiness and authorized acceptance remain unsupported ✓The critical defect and absent owner decision leave release readiness unsupported.
- Document the test completion rate and proceedDocumentation cannot replace defect resolution or authorized business acceptance.
- Recommend conditional deployment while operations manage the defect after productionDeployment would shift unresolved critical risk without authorized business acceptance.
- Declare readiness because most tests passedA high pass rate does not overcome a remaining critical defect.
A critical defect and missing business-owner acceptance prevent a readiness conclusion.
6. Design is adequate: What conclusion is BEST?
- The releases are effective because most sampled releases complied with requirements.Missing authorization and testing records demonstrate operating failures despite majority compliance.
- Design is adequate; operation is unsupported by sampled exceptions. ✓The requirements are present, but exceptions undermine evidence of operating effectiveness.
- Approval proves the procedure is effective.Approval demonstrates design evidence, not consistent operation across sampled releases.
- The procedure is ineffective by design because sampled releases lacked required evidence.The approved procedure contains appropriate requirements despite operating-performance exceptions.
Design is present, but sampled exceptions undermine operating effectiveness evidence.
7. Delay cutover until rejected and inaccurate records are: Which recommendation is most appropriate?
- Reconcile rejected records, then document migration results without validating accepted values.Reconciliation alone does not address inaccurate values already accepted.
- Proceed while monitoring rejected records after cutover.Post-cutover monitoring leaves known conversion errors affecting operations.
- Proceed because source and target record counts agree.Matching counts do not demonstrate accurate values or complete conversion.
- Delay cutover until rejected and inaccurate records are corrected and retested. ✓Known completeness and accuracy failures prevent reliable migration assurance before cutover.
Delay cutover until completeness, accuracy, reconciliation, and retesting support migration reliability.
8. Expand review to objectives: What should the auditor recommend to improve assurance scope?
- Conclude implementation success from uptime alone.Uptime alone does not demonstrate objectives, benefits, or control effectiveness.
- Repeat installation testing before reviewing business outcomes and operational lessons.Repeating installation tests does not address omitted business assurance areas.
- Expand review to objectives, benefits, controls, outcomes, and lessons learned. ✓A post-implementation review should assess stabilized results beyond technical installation.
- Delay benefits and control review until the next year.Stabilization already permits timely evaluation of objectives and operational results.
Expand post-implementation assurance beyond installation and uptime to business outcomes and controls.
9. Significant scope: Which project-governance gap is most consequential?
- The project should have used a different development methodology.Methodology choice does not cure unauthorized scope and risk decisions.
- The steering committee should review every routine task before continuation.Governance oversight should target significant changes, not routine project activity.
- Significant scope, cost, and risk changes lacked required governance authorization. ✓Governance must assign decision rights for material changes affecting project exposure.
- The project manager lacked technical expertise.Technical expertise does not determine authority for significant project changes.
Material scope and risk changes require governance authorization, not unilateral project-manager approval.
10. Verify operational feasibility assessment and sponsor: What should the auditor do next?
- Verify operational feasibility assessment and sponsor approval. ✓Operational feasibility remains an unaddressed decision basis requiring evidence.
- Recalculate acquisition costs using an independent financial model.Costs were already addressed; the missing feasibility dimension remains operational impact.
- Recommend selecting the lowest-cost alternative immediately.Business cases compare benefits, risks, alternatives, and outcomes, not merely cost.
- Test postimplementation benefits before feasibility assessment is complete.Benefits testing is premature while operational feasibility remains unevaluated.
Verify the missing operational feasibility assessment and its authorized business acceptance.
11. Require traceable requirements: How should the auditor evaluate management’s proposed response?
- Accept sprint demonstrations when developers confirm completion without business authorization.Developer confirmation does not replace authorized business acceptance or traceability.
- Accept the response because agile projects need no formal controls or acceptance.Agile delivery still requires traceable requirements, testing, and acceptance evidence.
- Require waterfall documentation before any agile development continues.Agile is acceptable when necessary requirements and controls remain traceable.
- Require traceable requirements, security, testing, and authorized acceptance in agile delivery. ✓Methodology does not remove essential governance, control, testing, or acceptance requirements.
Agile may vary delivery practices but cannot eliminate traceability, testing, security, or acceptance.
12. The control operated ineffectively during the tested: How should the auditor interpret these results?
- The control is effective because all sampled transactions were authorized.Authorization does not compensate for omitted reconciliation procedures.
- The control design is invalid because authorization was tested.Testing authorization does not indicate that the control design itself is invalid.
- The control operated ineffectively during the tested period. ✓Missing required reconciliation demonstrates an operating failure despite authorization evidence.
- The control is effective because three missed days are immaterial without losses.Observed nonperformance requires evaluation; absence of losses does not prove operation.
Authorization passed, but missed reconciliation demonstrates ineffective operation during tested days.
336 more Information Systems Acquisition, Development and Implementation questions
The remaining 336 questions in this domain are part of the full CISA bank — 2900 questions, every option explained. Start with the free five-minute check and see your score per domain.
Test your CISA readiness — freeOther CISA domains
- Information Systems Operations and Business Resilience — 754 questions →
- Protection of Information Assets — 754 questions →
- Information Systems Auditing Process — 522 questions →
- Governance and Management of IT — 522 questions →
- All 2900 CISA questions →
- CISA certification: requirements, cost and exam format →