PRINCE2 Foundation Practices: 840 practice questions
7-day money-back guarantee — full refund within 7 days of purchase if you've completed under 20% of the questions. See pricing →
Certifications Tools Flashcards Career Paths Exam Guides Blog Pricing For Teams About

PRINCE2 Foundation Practices: 840 practice questions

PRINCE2 Foundation 840 questions 12 shown free

12 of the 840 Practices questions in the Certsqill PRINCE2 Foundation bank, shown in full below. Each one carries an explanation for every option, not just the correct one — the wrong answers are where the marks go.

Preparing for PRINCE2 Foundation? Take the free 5-min readiness check →

1. Acceptance criteria: Which concept provides measurable conditions for that acceptance?

Easy
During a billing-system rollout, the sponsor asks what defines final acceptance of the project product. Which concept provides measurable conditions for that acceptance?
  1. Acceptance criteria ✓
    Acceptance criteria are measurable conditions that must be met before the final project product is accepted.
  2. Quality specifications
    Quality specifications define measurable product-level criteria, but they are not the overall conditions for final acceptance.
  3. User quality expectations
    User quality expectations express broad needs, while acceptance criteria state measurable conditions required for final acceptance.
  4. Quality register
    The quality register records planned and completed quality-control activities and their results, rather than acceptance conditions.
The trap
Confuses a quality record with defined acceptance requirements. Confuses product-level specifications with overall final acceptance conditions. Mistakes broad user needs for measurable acceptance conditions.

Acceptance criteria state measurable conditions for final acceptance of the project product.

2. Business case practice: Which practice provides the relevant review?

Medium
An inventory-improvement project reaches a stage boundary. Forecast costs and benefits have changed, so the board must decide whether continued work remains justified. Which practice provides the relevant review?
  1. Risk practice for identifying uncertain events and responses.
    Risk information can inform the review, but risk practice is not the complete assessment of continued justification.
  2. Quality practice for checking product fitness against requirements.
    The quality practice checks products against requirements, not whether continued investment remains justified.
  3. Plans practice for delivery structure and control.
    The plans practice addresses planned work, resources, costs, timing, and controls rather than continued justification.
  4. Business case practice ✓
    The business case practice reviews whether the project remains desirable, viable, and achievable using updated information.
The trap
Confuses planning information with the justification decision. Confuses product fitness with project justification. Treats risk management as the whole business-case review.

The business case practice reviews continued project justification.

3. Quality control: Which quality concept describes this activity?

Medium
A charity donation platform team checks a completed product against its agreed product specifications. Which quality concept describes this activity?
  1. Quality control ✓
    Quality control checks products against their agreed specifications to determine whether they meet defined requirements.
  2. Quality planning
    Quality planning defines criteria, descriptions, methods, and roles before quality-control activities are performed.
  3. Quality assurance
    Quality assurance provides planned, systematic confidence, usually independently of the project team, rather than checking one product.
  4. Project assurance
    Project assurance is the board’s responsibility across business, user, and supplier interests, not product inspection itself.
The trap
Confuses independent systematic confidence with product checking. Confuses governance assurance with checking a product. Confuses defining checks with performing the check.

Quality control checks products against agreed specifications.

4. A business opportunity: What is it?

Easy
During equipment replacement, a supplier suggests an additional service that could improve future operating benefits. The possibility is currently being considered, not yet agreed. What is it?
  1. A positive risk
    A positive risk is an uncertain prospective event, whereas the described item is classified as a business-opportunity issue.
  2. A request for change
    A request for change proposes altering an approved baseline, whereas this possibility concerns a potential beneficial opportunity.
  3. A business opportunity ✓
    A business opportunity is a positive issue representing a potential beneficial outcome requiring project-management consideration.
  4. A benefit
    A benefit is a measurable advantageous improvement, while this is only a possibility being considered.
The trap
Confuses a potential opportunity with a realized measurable benefit. Treats a potential benefit as a proposed baseline change. Confuses risk uncertainty with the stated issue classification.

A business opportunity is a positive issue representing a possible beneficial outcome.

5. Progress practice: Which concept is being applied?

Easy
In a school refurbishment, actual progress remains within the project manager’s agreed tolerances. The project manager compares achievement and forecasts with the plan to control delivery. Which concept is being applied?
  1. Exception management after a forecast beyond tolerance
    Exception management is required when a forecast goes beyond agreed tolerance; the scenario explicitly states that progress remains within tolerance.
  2. Quality practice for checking product specifications
    Quality practice checks products against agreed specifications, whereas this activity evaluates delivery performance against plans and tolerances.
  3. Progress practice ✓
    The progress practice compares achievement and forecasts with plans and tolerances to support control before thresholds are exceeded.
  4. Plans
    Plans provide the baselines and controls for delivery, but the described activity is comparing achievement and forecasts against them.
The trap
Confuses the management baseline with the activity of monitoring progress. Confuses product checking with performance comparison. Assumes any comparison activity is an exception.

The progress practice compares achievement and forecasts with plans and tolerances.

6. Stage plan: The sentence reads: “The [ ?

Hard
A membership service project is preparing detailed information for the manager to control the next management stage. The sentence reads: “The [ ? ] describes that stage’s products, work, resources, costs, timing, and controls.” Select ONE term.
  1. Stage plan ✓
    A stage plan provides detailed information for the manager to control a particular management stage.
  2. Project plan
    The project plan provides the high-level overall baseline, rather than detailed control information for one management stage.
  3. Exception plan
    An exception plan replaces an affected plan after approval when tolerances are forecast to be exceeded.
  4. Team plan
    A team plan supports work-package delivery where needed, rather than controlling the whole management stage.
The trap
Confuses overall project planning with stage-level planning. Confuses replacement planning after exception with routine stage planning. Confuses delivery-level planning with management-stage planning.

A stage plan gives the manager detailed control information for one management stage.

7. Risk exposure: Which term applies?

Easy
A charity donation platform records several risks affecting fundraising, security, and delivery objectives. Management wants one view of the total amount of objectives currently at risk. Which term applies?
  1. Risk exposure ✓
    Risk exposure represents the aggregate amount of project objectives currently at risk from identified risks.
  2. Residual risk
    Residual risk is the remaining risk after responses, not the aggregate exposure across the project’s objectives.
  3. Risk tolerance
    Risk tolerance defines agreed limits and escalation boundaries, rather than aggregating current exposure across objectives.
  4. Risk appetite
    Risk appetite expresses willingness to take risk, not the combined amount of objectives exposed to identified risks.
The trap
Confuses post-response risk with aggregated exposure. Confuses acceptable limits with the amount at risk. Confuses willingness to take risk with measured exposure.

Risk exposure is the aggregate amount of objectives currently at risk.

8. Superseded: The earlier starting-up document has therefore been [ ?

Medium
For a supplier-portal project, the project board approves the PID during initiation. The earlier starting-up document has therefore been [ ? ]. Select ONE term.
  1. Archived
    Archiving may describe record handling, but it is not the PRINCE2 relationship created when the PID replaces the brief.
  2. Superseded ✓
    The project brief is superseded by the PID, which establishes how the project is justified, organized, and controlled.
  3. Escalated
    Escalation sends matters beyond delegated authority for a decision; it does not replace the project brief with the PID.
  4. Baselined
    Baseline status concerns approved products subject to change control, not the relationship between the project brief and PID.
The trap
Confuses governance escalation with document progression. Confuses approval status with replacement of an earlier document. Confuses record storage with the formal document relationship.

The project brief is superseded by the PID during project initiation.

9. Product register: Which management product is most relevant?

Medium
An inventory-improvement team needs a current record showing which products exist and what acceptance information applies to them. Which management product is most relevant?
  1. Project log
    The project log collects evolving records, while the product register specifically identifies products and acceptance information.
  2. Product register ✓
    The product register identifies products and records relevant acceptance information for the project.
  3. Issue register
    The issue register records matters needing project-management consideration, not the project’s product inventory and acceptance details.
  4. Quality register
    The quality register records quality-control activities and results, rather than identifying the project’s products and acceptance information.
The trap
Confuses issue tracking with product tracking. Confuses quality activity records with product identification. Chooses a broad collection record over the specific product record.

The product register identifies project products and their acceptance information.

10. 1 and 3: Select ONE pair of statements that is correct.

Easy
A membership-service project is reviewing how issues are handled. Consider these statements:
1. Any stakeholder can raise an issue.
2. Every issue must change an approved baseline.
3. Issues may be positive as well as negative.
4. A manager may approve beyond delegated authority when the outcome is beneficial.
Select ONE pair of statements that is correct.
  1. 2 and 4
    Neither statement is correct: issues need not change baselines, and authority cannot be exceeded without proper authorization.
  2. 2 and 3
    Issues may be positive, but not every issue changes an approved baseline; some require consideration without baseline change.
  3. 1 and 4
    Any stakeholder can raise an issue, but a manager cannot approve beyond delegated authority merely because the outcome is beneficial.
  4. 1 and 3 ✓
    Any stakeholder can raise an issue, and issues include positive opportunities as well as negative matters.
The trap
Combines a true classification with an overbroad baseline statement. Assumes every issue changes baselines and benefits expand authority. Combines one true issue rule with an invalid authority claim.

Issues can be raised by any stakeholder and may represent positive opportunities.

11. quality register: The [ ?

Medium
For a renewable energy installation, quality planning must define criteria, descriptions, and the approach. The [ ? ] records planned and completed quality-control activities and their results.
  1. product register
    The product register identifies products and their acceptance, rather than documenting quality-control activity results.
  2. quality management approach
    The quality management approach describes methods, standards, responsibilities, and arrangements for managing quality.
  3. quality register ✓
    The quality register records planned and performed quality-control activities together with their results.
  4. product description
    A product description defines one product’s purpose, composition, quality criteria, and development information.
The trap
This establishes the approach rather than recording control results. Confuses product definition with recording completed control activities. Confuses product identification with quality-control recording.

The quality register records planned and performed quality-control activities and their results.

12. baseline: A request for change is a proposal to modify an approved [ ?

Medium
During a billing system rollout, a stakeholder proposes altering an approved requirement. A request for change is a proposal to modify an approved [ ? ].
  1. baseline ✓
    A request for change proposes altering an approved baseline and therefore requires assessment and authorized decision.
  2. quality register
    The quality register records control activities and results, not the approved project products being proposed for change.
  3. work package
    A work package authorizes assigned delivery work; it is not the general object of every change request.
  4. risk response
    A risk response addresses uncertainty, whereas a request for change proposes altering an approved baseline.
The trap
Confuses a quality record with an approved baseline. Confuses managing uncertainty with changing approved scope. Treats one delivery assignment as the baseline.

A request for change proposes altering an approved baseline and requires authorized consideration.

828 more Practices questions

The remaining 828 questions in this domain are part of the full PRINCE2 Foundation bank — 1400 questions, every option explained. Start with the free five-minute check and see your score per domain.

Test your PRINCE2 Foundation readiness — free

Other PRINCE2 Foundation domains

Part of the Certsqill PRINCE2 Foundation question bank · Practices · Every answer, right and wrong, comes with its own explanation.