PRINCE2 Foundation Processes: 210 practice questions
12 of the 210 Processes questions in the Certsqill PRINCE2 Foundation bank, shown in full below. Each one carries an explanation for every option, not just the correct one — the wrong answers are where the marks go.
Preparing for PRINCE2 Foundation? Take the free 5-min readiness check →
1. To verify acceptance and handover: During closing a project, what is the purpose of the project manager’s fina
- To verify acceptance and handover, assess project performance, record follow-on actions, and recommend closure ✓Closing verifies acceptance and handover, evaluates performance, records follow-on actions, and prepares the closure recommendation.
- To authorize the project’s closure and issue final direction to the delivery teamThe project board authorizes closure; the project manager prepares the recommendation rather than granting that authorization.
- To prepare the next stage plan and update the project plan for approvalThose activities belong to managing a stage boundary, not the final purpose of closing the project.
- To assign work packages and monitor outstanding delivery activities during the stageAssigning and monitoring work packages is controlling a stage, not completing project closure activities.
Closing confirms acceptance, evaluates results, records follow-on actions, and recommends closure for authorization.
2. Confirm completion: Which purpose best describes closing the project?
- Assign delivery work packages and monitor their completion throughout the stageWork-package assignment and monitoring are responsibilities within controlling a stage during delivery.
- Authorize the project and approve its initiation plan before delivery beginsProject authorization and initiation planning occur earlier, through directing and initiating activities.
- Review the current stage and prepare the plan for the next management periodReviewing a stage and preparing the next plan describes managing a stage boundary.
- Confirm completion, capture follow-on actions, and recommend that the project be closed ✓Closing confirms completion and acceptance, captures follow-on actions, and produces a recommendation for authorized closure.
Closing confirms the project’s completion and prepares follow-on information and a closure recommendation.
3. To review the stage: Which purpose describes managing a stage boundary?
- To assign work packages and manage issues during the current stageAssigning work packages and handling issues during delivery belong to controlling a stage.
- To review the stage, update justification and plans, and prepare the next or exception plan ✓Managing a stage boundary reviews the completed stage, updates key plans and justification, and prepares the next or exception plan.
- To confirm final handover and recommend closure of the entire projectFinal handover and a closure recommendation belong to closing a project, not every stage boundary.
- To authorize the next stage and provide direction across the project lifecycleThe project board authorizes the next stage through directing a project after receiving boundary information.
Managing a stage boundary reviews the current stage and prepares information and plans for the next decision.
4. Starting up a project: Which process is illustrated?
- Starting up a project ✓Starting up a project follows the mandate and checks whether the project is worthwhile and viable enough to initiate.
- Managing a stage boundaryManaging a stage boundary reviews a stage and prepares a subsequent or exception plan, not the initial project check.
- Directing a projectDirecting concerns project board decisions and authority across the lifecycle, rather than the initial viability work.
- Initiating a projectInitiating develops the detailed justification, plans, approaches, and PID after the initial viability check.
Starting up checks whether the mandated project is worthwhile and viable enough to initiate.
5. To establish whether the proposed project is worthwhile: Why does starting up the project create an outline bu
- To confirm final acceptance and document benefits reviews after migrationAcceptance and benefits-review planning at project completion are closing activities, not starting-up purposes.
- To authorize initiation and approve the project board’s decisions for deliveryThe project board authorizes initiation through directing a project; starting up supplies information for that decision.
- To establish whether the proposed project is worthwhile and viable enough to initiate ✓Starting up creates initial information so the organization can judge whether the proposed project merits detailed initiation.
- To provide the detailed justification and management approaches required for project authorizationDetailed justification, management approaches, and the PID are established during initiating a project.
Starting up supplies enough initial information to judge whether detailed project initiation is justified.
6. 1 and 3: Directing a project occurs only during the first stage.
1. The project board authorizes initiation.
2. Directing a project performs the team’s day-to-day work.
3. The project board can authorize closure.
4. Directing a project occurs only during the first stage.
- 2 and 3Statement 3 is true, but statement 2 is false because directing does not perform day-to-day team work.
- 2 and 4Both statements are false: directing is not day-to-day delivery and is not limited to the first stage.
- 1 and 4Statement 1 is true, but statement 4 is false because directing spans the project lifecycle, not only its first stage.
- 1 and 3 ✓Statement 1 is true because the board authorizes initiation; statement 3 is true because it also authorizes closure.
The board authorizes initiation and closure; directing spans the lifecycle without performing day-to-day delivery.
7. 1 and 3: The process authorizes project closure.
1. The project manager controls the stage.
2. The project board performs the daily work-package monitoring.
3. The process handles issues and risks during the stage.
4. The process authorizes project closure.
- 2 and 3Statement 3 is true, but statement 2 is false because the project manager controls daily stage monitoring.
- 1 and 3 ✓Statement 1 is true because the project manager controls the stage; statement 3 is true because issues and risks are handled there.
- 2 and 4Both statements are false: the board does not perform daily monitoring, and the process does not authorize closure.
- 1 and 4Statement 1 is true, but statement 4 is false because closure authorization belongs to the project board.
Controlling a stage is the project manager’s process for monitoring work and handling issues and risks.
8. 1 and 2: The delivery team authorizes project initiation.
1. The project brief is established during starting up.
2. The project manager is established during starting up.
3. The PID is finalized during starting up.
4. The delivery team authorizes project initiation.
- 2 and 4Statement 2 is true, but statement 4 is false because initiation authorization belongs to the project board.
- 1 and 2 ✓Statement 1 is true because starting up establishes the brief; statement 2 is true because it establishes the project manager.
- 3 and 4Both statements are false: the PID follows starting up, and the delivery team does not authorize initiation.
- 1 and 3Statement 1 is true, but statement 3 is false because the PID is developed during initiating a project.
Starting up establishes the project brief and project manager; detailed PID development and authorization follow later.
9. 1 and 3: Closing a project authorizes its own closure.
1. The project manager verifies acceptance and handover.
2. The project board recommends closure.
3. The project manager recommends closure.
4. Closing a project authorizes its own closure.
- 1 and 3 ✓Statement 1 is true because the manager verifies acceptance and handover; statement 3 is true because the manager recommends closure.
- 1 and 4Statement 1 is true, but statement 4 is false because the project board authorizes closure.
- 2 and 4Both statements are false: the board authorizes closure, while the manager recommends it.
- 2 and 3Statement 3 is true, but statement 2 is false because the manager, not the board, prepares the recommendation.
The project manager verifies handover and recommends closure; the board separately authorizes that closure.
10. To establish a sufficiently detailed basis for authorizing: What is the purpose of this work?
- To authorize stages, exceptions, and closure throughout the project lifecycleThose authorization decisions belong to directing a project and remain the project board’s responsibility.
- To verify final acceptance, record follow-on actions, and recommend project closureThose activities belong to closing a project after the project’s products have been delivered.
- To establish a sufficiently detailed basis for authorizing and managing the project ✓Initiating creates the detailed justification, plans, approaches, and PID needed to authorize and manage the project.
- To decide whether the initial proposal is worthwhile enough to begin detailed initiationThat initial worthwhileness and viability check is the purpose of starting up a project.
Initiating develops the detailed basis, plans, approaches, and PID needed for project authorization and management.
11. Starting up a project: Which process is this?
- Starting up a project ✓Starting up checks viability, establishes key roles, considers lessons, and develops the initial project direction.
- Directing a projectDirecting concerns project board decisions and authorization rather than the initial viability assessment.
- Closing a projectClosing verifies acceptance, evaluates performance, records follow-on actions, and recommends project closure.
- Initiating a projectInitiating develops detailed justification, plans, and management approaches after the initial viability check.
Starting up a project establishes whether the mandated work is worthwhile and viable enough to initiate.
12. 1 and 2: Select ONE pair of statements that is correct.
1. The delivery team accepts, executes, and delivers work-package products.
2. The delivery team reports to the project manager.
3. Controlling a stage authorizes the project.
4. Managing product delivery occurs only at stage boundaries.
Select ONE pair of statements that is correct.
- 1 and 3Statement 1 is correct, but project authorization belongs to directing a project, not controlling a stage.
- 2 and 4Statement 2 is correct, but product delivery may run alongside stage control, not only at boundaries.
- 3 and 4Neither statement is correct: authorization is directing work, and delivery is not restricted to boundaries.
- 1 and 2 ✓Statements 1 and 2 are correct: managing product delivery covers team delivery and reporting to the project manager.
Managing product delivery covers accepting, executing, and delivering work-package products while reporting to the project manager.
198 more Processes questions
The remaining 198 questions in this domain are part of the full PRINCE2 Foundation bank — 1400 questions, every option explained. Start with the free five-minute check and see your score per domain.
Test your PRINCE2 Foundation readiness — freeOther PRINCE2 Foundation domains
- Practices — 840 questions →
- People — 196 questions →
- Principles — 112 questions →
- Key concepts — 42 questions →
- All 1400 PRINCE2 Foundation questions →
- PRINCE2 Foundation certification: requirements, cost and exam format →